Enable JavaScript to ensure website accessibility seabet io Majorsville Cryogenic #4

seabet io Majorsville Cryogenic #4

seabet io Majorsville Cryogenic #4
Client

seabet io Liberty Midstream

Location Pin

Dallas, West Virginia

  • 3,400 cubic yards of concrete
  • 12,000 yards of dirt
  • 665 lineal feet of pipe rack steel
  • Electrical ductbank
  • Construction of masonry building
  • Accelerated schedule

Project Details

The scope of work included foundations for pipe racks, switchgear building, compressor building, and control and motor control center buildings; residual compressor foundations; USM and Vortex foundations; and miscellaneous tank foundations, as well as underground electrical excavation and backfill.